What does an adverse variable overhead efficiency variance indicate and what might be the cause?

掃碼查看暗號(hào),即可獲得解鎖答案!

點(diǎn)擊獲取答案
Chapter20Standardcosting

Variable overhead

It indicates that the work completed took longer than it should have done. It could be caused by employing semi-skilled workers instead of skilled workers who will take longer to complete the job.

多做幾道

Explain what is meant by standard costing

Explain what is meant by a standard cost

Describe four types of standard.

Explain what is meant by a standard hour.

Give five possible sources of information from which a standard materials price may be estimated.